Subhub on Ballast Trials

QED Naval recently returned to Subhub following the completion of the tow to tidy things up and secure Subhub for the initial ballast system and flow augmentation trials.

The moorings were reset so that Subhub now aligns to flow on the flood and ebb tides where flow speeds of up to 1m/s are experienced which is ideal for conducting the initial ballast system trials, the company explained.

Some of the marker buoys were reset and the umbilical and operations tether unraveled and stretched out. The umbilical allows the remote control of the Subhub platform from the support vessel which is a barge in this case.

The umbilicals are connected into the Subsea Manifold which is an subsea junction box so when the Subhub is installed all the services can be disconnect from the support vessel housing the air compressors, HPU, generators and control panels. It can then be lowered to the seabed so the support vessel can demobilised and site cleared of any visual impact. Equally, the Subsea Manifold can be easily retrieved and the systems connected up to take control of the Subhub again.

The video below also shows the final action of the day which was to make some modifications to tidal turbines.

Share this article

Follow Marine Energy

Events>

<< May 2019 >>
MTWTFSS
29 30 1 2 3 4 5
6 7 8 9 10 11 12
13 14 15 16 17 18 19
20 21 22 23 24 25 26
27 28 29 30 31 1 2

Seawork International 2019

Seawork International is the largest and fastest growing international commercial marine and workboat exhibition and conference…

read more >

ASEAN SUSTAINABLE ENERGY WEEK

ASEAN Sustainable Energy Week 2019 will feature the very latest innovative energy sources along with…

read more >

3rd World Congress on Wind & Renewable Energy

Conference Series warmly invites all the participants from all over the world to attend…

read more >

OCEANS 2019

OCEANS is the bi-annual event for global marine technologists, engineers, students…

read more >