James Fisher lays Wave Hub cables

James Fisher Marine Services has completed the subsea cable installation works at the Wave Hub test site off Cornwall, UK.

James Fisher finalized the works on August 12, and Aker Wayfarer and MTS Xplorer vessels which were used for the operation are clear of the site.

All equipment has been installed and the electrical system is live, Wave Hub informed.

The offshore works included the installation of four 33 kV cable extensions laid from the Wave Hub Safety Zone out to each developer berth.

The works also included the installation of associated cable connectors, bend restrictors and abrasion protection, as well as cable support and stabilisation measures.

The worth of the contract for the execution of works, awarded in May this year to James Fisher, was £2.8 million.

Wave Hub provides shared offshore infrastructure for the demonstration and proving of offshore renewable energy technologies.

My location

Get Directions

Share this article

Follow Marine Energy

Events>

<< Apr 2020 >>
MTWTFSS
30 31 1 2 3 4 5
6 7 8 9 10 11 12
13 14 15 16 17 18 19
20 21 22 23 24 25 26
27 28 29 30 1 2 3

AWTEC2020

AWTEC 2020 aims to provide an opportunity to exchange, learn, interact and network on all multidisciplinary…

read more >

PV Korea 2020 (The 17th Green Energy Expo)

This show is co-organized by the four major renewable energy associations of Korea.

read more >

All-Energy 2020

All-Energy is the UK’s leading and only full supply chain renewables and low carbon energy event for the private and public sector energy…

read more >

Offshore Energy Exhibition and Conference (OEEC) 2020

Offshore Energy addresses the technical, operational and commercial challenges associated with future sector growth.

read more >